RECOVERY AND STRENGTHENING OF PIERS AT ALAMOA

As per announcement made by DOCK Co., Alamoa terminal will suffer renovation in order to strengthening all of its piers with following dates:

Pier 01: From 01/11/2014 until 15/12/2014 (45 days) and also From 16/01/2015 until 01/03/2015 (45 days)
Pier 02: From 09/12/2013 until 23/01/2014 (45 days) and also Form 24/02/2014 until 10/04/2014 (45 days)
Pier 03: From 02/03/2015 until 31/05/2015 (90 days)
Pier 04: From 02/03/2015 until 31/05/2015 (90 days)

Obs.: All the above dates are subject to last minute changes announced by Dock Co.