FIRST PHASE OF DREDGING OF THE BERTHS AT PARANAGUA COMPLETED

Further to our previous news, kindly note that, as per Paranagua Dock Co. information, the first phase of the dredging services in the berths 209 until 217, was completed on March 13th 2014.

The second phase comprising the berths 206 until 208 shall start today (March 14th, 2014) at 07:00H p.m, and the third phase comprising the berths 201 to 205 (including SOCEPPAR – SHED 201 and PASA – SHED 204) will start tomorrow at 07:00hH a.m., both phases should be completed within 3-4 days.

During the above mentioned period, those berths will not operate. According to APPA (Paranagua Dock Co.) this schedule was made to avoid unberth the vessels, nevertheless if the vessel still operating by the time of the service, the ship will have to unberth and complete the operation after finishing of the dredging services.

Keeping you duly posted!

Paranagua Dock Co.